The third branch for a restaurant group. Brand consistency with the first two sites, plus outdoor seating to lift evening turnover.
Scope
- Site assessment
- Design
- Fit-out
- Licensing
- Fire safety
- Furniture
The challenge
- Brand standards: materials, lighting and flow had to match two existing sites
- Outdoor seating required a separate permission and clear means of escape
- Building management allowed noisy works only overnight
What we did
- Built a branch design standard; materials and furniture batch-ordered to cut lead times
- Indoor and outdoor seating applications submitted together to reduce rounds
- Day and night crews kept the schedule intact despite restrictions
Outcome
- 49
- Days, handover to opening
- 68
- Seats incl. outdoor
- 3
- Branches on one standard